Atico Produces 5.48 Million Pounds of Cu and 2,825 Ounces of Au in First Quarter 2018

Share

VANCOUVER, British Columbia, April 26, 2018 (GLOBE NEWSWIRE) -- Atico Mining Corporation (the "Company" or "Atico") (TSX-V:ATY) (OTC:ATCMF) announces its operating results for the three months ended March 31, 2018 from its El Roble mine. Production for the quarter totaled 5.48 million pounds of copper and 2,825 ounces of gold in concentrates, an increase of 9% and 11% for copper and gold, respectively, over the same period in 2017.

"We are very pleased to report our strongest operating quarter to date while maintaining steady state production levels and a robust start towards our 2018 operational objectives" said Fernando E. Ganoza, CEO. "For the remainder of the year, the Company will continue focusing on the regional and mine vicinity exploration programs with rigs currently drilling on surface and underground."

First Quarter Operational Highlights

  • Production of 5.48 million pounds of copper contained in concentrates; an increase of 9% over Q1 2017.
  • Production of 2,825 ounces of gold contained in concentrates; an increase of 11% over Q1 2017.
  • Average processed tonnes per day of 812, no significant change over Q1 2017.
  • Copper head grade of 3.80%, a decrease of 2% over Q1 2017.
  • Gold head grade of 2.03 grams per tonne; an increase of 6% over Q1 2017.
  • Copper and gold recovery of 94.0% and 62.8%; no significant change for copper and a decrease of 5% for gold over Q1 2017.

First Quarter Operational Review

Processed ore was ahead of Company budget for the first quarter. The increase in higher copper and gold output for the quarter relative to Q1 2017 is mostly explained by an 11% increase in processed ore. Copper recoveries maintained their highs and slightly improved when compared to the same period last year, while gold recoveries during the quarter were in line with Company projections. Gold recovery decrease is due to an increase in the copper content in the concentrate, this increase in the copper content in the concentrate provides a net economic benefit offsetting the decrease in gold recovery. The Company will continue to explore improving the copper content in the concentrate in the following quarters while increasing the gold recovery. 

During the quarter the Company delivered only one concentrate shipment due to lack of vessel availability, this resulted in a significantly higher than usual concentrate ending inventory going into the second quarter.

The operation remains on track to deliver on set guidance throughout the remainder of the year.

First Quarter Operational Details

  Q1 2018 Total   Q1 2017 Total   % Change  
Production (Contained in Concentrates)          
Copper (000s pounds) 5,476   5,046   9 %
Gold (ounces) 2,825   2,550   11 %
Mine          
Tonnes of ore mined 67,022   63,468   6 %
Mill          
Tonnes processed 69,499   62,885   11 %
Tonnes processed per day 812   810   Nil %
Copper grade (%) 3.80   3.89   -2 %
Gold grade (g/t) 2.03   1.92   6 %
Recoveries          
Copper (%) 94.0   93.5   1 %
Gold (%) 62.8   65.8   -5 %
Concentrates          
Copper and Gold Concentrates (dmt) 11,474   10,566   9 %
           
Payable copper produced (000s lbs) 5,202   4,790   9 %

Note: Metal production figures are subject to adjustments based on final settlement.

2018 Operational Guidance

The Company is basing 2018 guidance on year ended December 31, 2017 financial and production results. Please refer to Cautionary Note on Forward Looking Statements at the end of this document.

The Company set the following objectives for 2018 at the El Roble mine:

  • Process between 270,000 and 275,000 tonnes, an increase of 5% to 7.5% over 2017.
  • Maintain copper recovery above 93% and 62% for gold.
  • Maintain an average copper head grade between 3.5% and 3.7%
  • Maintain an average gold head grade between 1.8 g/t and 2.0 g/t
  • Increase production between 40,000 and 42,000 dry tonnes of concentrate.
  • Maintain production between 9,000 and 9,400 tonnes of copper.
  • Maintain production between 9,700 and 10,000 ounces of gold.
  • Increase the mill mechanical availability to 95% and reach 330 days worked.
  • Continue increasing the safety and environmental standards.

El Roble Mine

The El Roble mine is a high grade, underground copper and gold mine with nominal processing plant capacity of 800 tonnes per day, located in the Department of Choco in Colombia. Its commercial product is a copper-gold concentrate.

Since obtaining control of the mine on November 22, 2013, Atico has upgraded the operation from a historical nominal capacity of 400 tonnes per day.

El Roble has a measured and indicated resource of 1.87 million tonnes grading 3.46% copper and 2.27 g/t gold, at a cut-off grade of 0.93% copper equivalent. Mineralization is open at depth and along strike and the Company plans to further test the limits of the resource.

On the larger land package, the Company has identified a prospective stratigraphic contact between volcanic rocks and black and grey pelagic sediments and cherts that has been traced by Atico geologists for ten kilometers. This contact has been determined to be an important control on VMS mineralization on which Atico has identified numerous target areas prospective for VMS type mineralization occurrence, which is the focus of the current surface drill program at El Roble.

Qualified Person

Mr. Thomas Kelly (SME Registered Member 1696580), advisor to the Company and a qualified person under National Instrument 43-101 standards, is responsible for ensuring that the technical information contained in this news release is an accurate summary of the original reports and data provided to or developed by Atico.

About Atico Mining Corporation

Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America. The Company operates the El Roble mine and is pursuing additional acquisition opportunities. For more information, please visit www.aticomining.com. 

ON BEHALF OF THE BOARD

Fernando E. Ganoza
CEO
Atico Mining Corporation

Trading symbols: TSX.V: ATY | OTC: ATCMF

Investor Relations
Igor Dutina
Tel: +1.604.633.9022

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No securities regulatory authority has either approved or disapproved of the contents of this news release. The securities being offered have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the ''U.S. Securities Act''), or any state securities laws, and may not be offered or sold in the United States, or to, or for the account or benefit of, a "U.S. person" (as defined in Regulation S of the U.S. Securities Act) unless pursuant to an exemption therefrom. This press release is for information purposes only and does not constitute an offer to sell or a solicitation of an offer to buy any securities of the Company in any jurisdiction.

Cautionary Note Regarding Forward Looking Statements

This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation the use of net proceeds, are forward-looking statements. Forward- looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs; the need to obtain additional financing to maintain its interest in and/or explore and develop the Company's mineral projects; uncertainty of meeting anticipated program milestones for the Company's mineral projects; and other risks and uncertainties disclosed under the heading "Risk Factors" in the prospectus of the Company dated March 2, 2012 filed with the Canadian securities regulatory authorities on the SEDAR website at  www.sedar.com

The Company has not based its production decisions and ongoing mine production on mineral reserve estimates, preliminary economic assessments or feasibility studies, and historically such projects have increased uncertainty and risk of failure. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Non-GAAP Financial Measures

The items marked with a "(1)" are alternative performance measures and readers should refer to Non-GAAP Financial Measures in the Company's Management's Discussion and Analysis for the nine months ended September 30, 2016 as filed on SEDAR and as available on the Company's website for further details.




This announcement is distributed by Nasdaq Corporate Solutions on behalf of Nasdaq Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: Atico Mining Corporation via Globenewswire

About GlobeNewswire

GlobeNewswire
GlobeNewswire



Subscribe to releases from GlobeNewswire

Subscribe to all the latest releases from GlobeNewswire by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from GlobeNewswire

HMS Networks publicerar årsredovisning för 202327.3.2024 08:30:00 CET | Pressmeddelande

HMS Networks årsredovisning för 2023 finns nu tillgänglig på koncernens hemsida: www.hms-networks.com. Tryckt version av årsredovisningen kommer finnas tillgänglig i mitten av april. Beställning sker genom att skicka ett mejl till reception@hms.se. Den svenska årsredovisningen finns även tillgänglig på HMS hemsida i European Single Electronic Format (ESEF). För mer information, vänligen kontakta: CEO Staffan Dahlström, telefon: 035-17 29 01 CFO Joakim Nideborn, telefon: 035-71 06 983 Denna information är sådan information som HMS Networks AB (publ) är skyldiga att offentliggöra enligt lag om värdepappersmarknaden. Informationen lämnades, genom angivna kontaktpersoners försorg, för offentliggörande den 27 mars 2024, 08:30 CET. HMS Networks AB (publ) är en marknadsledande leverantör av lösningar inom industriell informations- och kommunikationsteknologi (Industrial ICT). HMS utvecklar och tillverkar produkter under varumärkena Anybus®, Ixxat®, Ewon® och Intesis®. Utveckling sker på huvud

AB Traction: Kallelse till årsstämma i AB Traction25.3.2024 12:00:00 CET | Pressmeddelande

Årsstämma i AB Traction (publ) Aktieägarna i AB Traction (publ), org.nr. 556029-8654, kallas härmed till årsstämma torsdagen den 2 maj 2024 kl 17.00 på Hotel Kung Karl, Birger Jarlsgatan 21 A, Stockholm. ANMÄLAN Aktieägare som önskar delta i årsstämman ska dels vara registrerad som aktieägare i den av Euroclear Sweden AB förda aktieboken tisdagen den 23 april 2024, dels anmäla sig hos bolaget senast måndagen den 22 april 2024. Anmälan kan göras per post under adress AB Traction, Box 3314, 103 66 Stockholm, via e-post: post@traction.se eller i nödfall på telefon 08-506 289 00. Ange vid anmälan namn, adress, telefonnummer, person-/organisationsnummer, aktieinnehav och uppgifter om eventuella ombud/biträden. I de fall aktieägare avser att låta sig företrädas genom ombud bör fullmakt och övriga fullmaktshandlingar biläggas anmälan. Fullmaktsformulär finns tillgängliga på bolagets hemsida www.traction.se samt sänds till aktieägare som begär det och uppger sin postadress eller e-post. Om akt

Elanders publicerar års- och hållbarhetsredovisningen för 202325.3.2024 07:30:00 CET | Pressmeddelande

Idag, måndagen den 25 mars 2024, publicerar Elanders sin års- och hållbarhetsredovisning för verksamhetsåret 2023 på bolagets hemsida www.elanders.com. Års- och hållbarhetsredovisningen distribueras per post till de aktieägare som aktivt har beställt en tryckt version, vissa kunder och övriga intressenter. Elanders AB (publ) För ytterligare information kontakta: Magnus Nilsson, vd och koncernchef, telefon: +46 31 750 07 50 Denna information är sådan information som Elanders AB är skyldigt att offentliggöra enligt lagen om värdepappersmarknaden. Informationen lämnades för offentliggörande den 25 mars 2024 kl. 07.30 CET. Bilaga 2024-03-25 Elanders pressmeddelande - Elanders publicerar års- och hållbarhetsredovisningen för 2023

Kallelse till Elanders årsstämma 202421.3.2024 10:00:00 CET | Pressmeddelande

Aktieägarna i Elanders AB (publ) kallas till årsstämma som hålls fredagen den 19 april 2024, kl. 13.00 på Södra Porten, Flöjelbergsgatan 1 C, Mölndal. RÄTT ATT DELTA Rätt att delta i stämman har den som upptagits som aktieägare i den av Euroclear Sweden AB förda aktieboken avseende förhållandena torsdagen den 11 april 2024. Dessutom måste aktieägare senast den 15 april 2024 även ha anmält sin avsikt att delta i stämman. För att ha rätt att delta i stämman måste aktieägare som låtit förvaltarregistrera sina aktier, förutom att anmäla sig till stämman, inregistrera aktierna i eget namn hos Euroclear Sweden AB, så att aktieägaren blir införd i aktieboken per den 11 april 2024. Sådan registrering, som kan vara tillfällig (s.k. rösträttsregistrering), begärs hos förvaltaren enligt förvaltarens rutiner i sådan tid i förväg som förvaltaren bestämmer. Rösträttsregistreringar som gjorts senast den andra bankdagen efter den 11 april 2024 beaktas vid framställningen av aktieboken. I Elanders finn

HMS Networks AB:s årsstämma den 23 april 202415.3.2024 07:33:45 CET | Pressmeddelande

Aktieägarna i HMS Networks AB (publ), org. nr. 556661-8954, kallas härmed till årsstämma tisdagen den 23 april 2024 klockan 10.30 i bolagets lokaler, Stationsgatan 37, Halmstad. Inregistrering för stämman börjar kl. 09.30. Rätt att delta vid årsstämman Aktieägare som önskar delta vid årsstämman ska dels vara införd i den av Euroclear Sweden AB förda aktieboken måndagen den 15 april 2024, dels anmäla sitt deltagande senast onsdagen den 17 april 2024, gärna före klockan 16.00. Anmälan ska ske via telefon 035-17 29 00, skriftligen till HMS Networks AB, ”Årsstämma”, Box 4126, 300 04 Halmstad eller på www.hms-networks.com. Vid anmälan ska namn, person-/organisationsnummer, adress, telefonnummer dagtid och uppgift om eventuella biträden (högst två) anges. Ombud Aktieägare som företräds genom ombud ska utfärda fullmakt för ombudet. Den som företräder juridisk person ska tillhandahålla kopia av registreringsbevis eller motsvarande för den juridiska personen. Fullmakten får inte vara äldre än e

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
HiddenA line styled icon from Orion Icon Library.Eye