SEMAFO: Construction of Boungou Mine 91% Complete

Dela

Commissioning Advancing to Plan 

 


 

 

 


 

 

 

MONTREAL, April 19, 2018 (GLOBE NEWSWIRE) --  SEMAFO Inc. (TSX:SMF) (OMX:SMF) announced that construction of the Boungou Mine in Burkina Faso is 91% complete, and commissioning activities are advancing well with 10% already completed at the end of March.

Since launch of commissioning at the end of February, the crushing circuit equipment and water services have been tested and commissioned. The reclaim and grinding circuits, reagent and oxygen plants are also undergoing testing. Wet commissioning began at the end of March with the Corporation pumping water from the water storage facility to the raw water tanks for the processing plant. We are still in line to achieve our first gold pour early in the third quarter of 2018.
  
As at March 31, 2018, the following milestones had been reached:

  • Development on budget with US$194 million of the US$231 million capital expenditure incurred
  • Construction of the mine 91% complete
  • Completion of 98% of structural steel and mechanical installation
  • Piping installation 83% complete
  • The tailings storage facility is more than 95% complete
  • Power plant is 93% complete and partially operational
    • By end of May, the four sub-stations should be fully in service
  • The fuel depot is 93% complete
  • Over 90% of electrical and instrumentation installation has been completed
  • Installation of the cladding for the gold room is near completion
  • Recruitment of mine operator employees is proceeding to schedule
    • Training began in April for completion in May
  • Pre-stripping 77% completed with 14 million of the projected 18 million tonnes extracted
    • First ore hauled to the ROM pad at month-end
  • 1,643 personnel including contractors were employed on site, 87% of whom are Burkinabe
  • 4.9 million man-hours (485 days) have been worked without lost-time injury 

Cladding of Gold Room Nearly Complete

This photo is available at http://resource.globenewswire.com/Resource/Download/0d40760c-1206-4fe5-b08b-695ba187d7a7

CIP and Leaching Areas

This photo is available at http://resource.globenewswire.com/Resource/Download/cba201cd-f7d4-4c66-864b-2a5dc8a1a4ec

The table below presents the construction milestones for the Boungou Mine and their level of completion:

Table 1 - Construction Milestones as at March 31, 2018

This photo is available at http://resource.globenewswire.com/Resource/Download/4dc4dee0-e377-430e-95c8-309c820f0c01

To follow the construction progress, please view the following link to the Boungou Mine photo and video gallery on our website: http://www.semafo.com/English/news-and-media/Boungou-Media-Page/default.aspx

Conference Call
The Corporation will release first quarter operational and financial results on May 8, 2018 after market close. Interested parties are invited to join the conference call and webcast, which will be held at 8 a.m. EDT on May 9, 2018.

Tel. local & overseas: +1 (647) 788 4922
Tel. North America: 1 (877) 223 4471
Webcast: http://www.semafo.com/
Replay number: 1 (800) 585 8367 or 1 (416) 621 4642
Replay pass code: 9457847
Replay expiration: May 30, 2018

About SEMAFO

SEMAFO is a Canadian-based mining company with gold production and exploration activities in West Africa.  The Corporation operates the Mana Mine in Burkina Faso, which includes the high-grade satellite deposit of Siou, and is targeting production start-up of the Boungou Mine in the third quarter of 2018.  SEMAFO's strategic focus is to maximize shareholder value by effectively managing its existing assets as well as pursuing organic and strategic growth opportunities.

CAUTION CONCERNING FORWARD-LOOKING STATEMENTS
This press release contains forward-looking statements. Forward-looking statements involve known and unknown risks, uncertainties and assumptions and accordingly, actual results and future events could differ materially from those expressed or implied in such statements. You are hence cautioned not to place undue reliance on forward-looking statements. Forward-looking statements include words or expressions such as "in line with", "achieve", "milestones", "will", "targeting", "pursuing", "growth", "opportunities" and other similar words or expressions. Factors that could cause future results or events to differ materially from current expectations expressed or implied by the forward-looking statements include the ability to achieve our first gold pour at Boungou early in the third quarter of 2018, the ability to meet all the construction milestones for the Boungou Mine in 2018, the ability to execute on our strategic focus, fluctuation in the price of currencies, gold or operating costs, mining industry risks, uncertainty as to calculation of mineral reserves and resources, delays, political and social stability in Africa (including our ability to maintain or renew licenses and permits) and other risks described in SEMAFO's documents filed with Canadian securities regulatory authorities. You can find further information with respect to these and other risks in SEMAFO's documents filed with Canadian securities regulatory authorities. You can find further information with respect to these and other risks in SEMAFO's 2017 Annual MD&A, and other filings made with Canadian securities regulatory authorities and available at www.sedar.com. These documents are also available on our website at www.semafo.com. SEMAFO disclaims any obligation to update or revise these forward-looking statements, except as required by applicable law.

The information in this release is subject to the disclosure requirements of SEMAFO under the Swedish Securities Market Act and/or the Swedish Financial Instruments Trading Act. This information was publicly communicated on April 19, 2018 at 7.00 a.m., Eastern Daylight Time.

For more information, contact

SEMAFO
John Jentz
Vice-President, Corporate Development & Investor Relations
Email: John.Jentz@semafo.com

Ruth Hanna
Analyst, Investor Relations
Email: Ruth.Hanna@semafo.com
Tel. local & overseas: +1 (514) 744 4408
North America Toll-Free: 1 (888) 744 4408
Website: www.semafo.com




This announcement is distributed by Nasdaq Corporate Solutions on behalf of Nasdaq Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: SEMAFO Inc. via Globenewswire

Om

NASDAQ OMX
NASDAQ OMX



Följ NASDAQ OMX

Abonnera på våra pressmeddelanden.

Senaste pressmeddelandena från NASDAQ OMX

Sciaky Receives Order for Multiple Electron Beam Additive Manufacturing (EBAM®) Systems to Strengthen America's Defense and Power Generation Programs21.5.2018 09:00Pressmeddelande

CHICAGO, May 21, 2018 (GLOBE NEWSWIRE) -- Sciaky, Inc., a subsidiary of Phillips Service Industries, Inc. (PSI) and leading provider of metal additive manufacturing (AM) solutions, announced today that it has received an order for multiple Electron Beam Additive Manufacturing (EBAM®) systems to bolster the nation's defense and power generation programs. Details of the project are confidential. "Sciaky has a long history of providing innovative solutions to America's military and power generation initiatives," said Scott Phillips, President and CEO of Sciaky, Inc. "Our EBAM process is the only industrial-grade metal 3D printing technology to produce large-scale parts for land, sea, air, and space applications." As the most widely scalable metal additive manufacturing solution in the industry (in terms of work envelope), Sciaky's EBAM systems can produce parts ranging from 8 inches (203 mm) to 19 feet (5.79 meters) in length. EBAM is also the fastest deposition process in the metal addit

Clean Motion skalar upp med mikrofabriker runt om i världen med hjälp av digital masterfabrik från Siemens.21.5.2018 08:11Pressmeddelande

Elfordonstillverkaren Clean Motion, tillverkarare av den elektriska trehjulingen Zbee, har en global expansionsstrategi som bygger på distribuerad lokal tillverkning i många, mindre fabriker nära slutkunden. För att lyckas med en sådan expansion är det viktigt att säkerställa en digitalt definierad produkt och tillverkningsprocess tillsammans med en centralt kontrollerad leverantörskedja. Clean Motion tar nu nästa steg i sin digitaliseringsprocess tillsammans med Siemens, där digitala tvillingar möjliggör en fullt digitaliserad virtuell produkt, tillverkningsprocess och fabrik. Clean Motion har inlett ett samarbete med Siemens och Virtual Engineering för att realisera sin digitaliseringsstrategi. Som en del av den strategin kommer en digital masterfabrik att byggas i Siemens PLM mjukvara. Fabriken kommer sedan möjliggöra anpassningar för införandet av nya varianter samt optimering av produktionsflöden. Clean Motion kommer kunna bygga upp ett stort antal oberoende fysiska fabriker och s

BK Ultrasound, Powered by Analogic, Launches bkSpecto Ultrasound System for Urology at the 2018 American Urological Association Annual Meeting18.5.2018 23:23Pressmeddelande

PEABODY, Mass., May 18, 2018 (GLOBE NEWSWIRE) -- Analogic Corporation (Nasdaq:ALOG), enabling the world's medical imaging and aviation security technology, today announced that it will launch the bkSpecto(TM) ultrasound system at the 113th AUA (American Urological Association) Annual Meeting, May 18-21, in San Francisco. bkSpecto-taken from the Latin word Specto, meaning 'I see'-is BK Ultrasound's all-new ultrasound platform designed for clinical practices. bkSpecto combines BK's advanced auto-optimization algorithms with faster processing to render exceptional anatomical imaging detail with minimal manual adjustment by the user. The system has a unique glass touch-based interface using BK's Tru-Sense(TM) technology to provide 'sightless navigation.' The interface enables tactile feedback with or without gloves, providing an intuitive, self-guided user experience. The interface is also customizable, enabling personalized and faster user workflows. The small footprint of bkSpecto makes

BIMobject AB: BIMobject publicerar årsredovisning för 201718.5.2018 17:25Pressmeddelande

BIMobject, som digitaliserar byggbranschen bland annat via molnbaserade plattformar, har idag publicerat årsredovisningen för 2017 på bolagets hemsida. "Det är med stolthet vi offentliggör årsredovisningen för året 2017 - ett år som för oss inte kan beskrivas annat än som 'explosivt'. Det är fantastiskt roligt att se hur vi fortsätter att effektivisera branscher som äntligen börjar se nyttan och digitaliseringens fulla potential. Att vi sedan har fyra starka trender som ger oss vind i seglet gör framtiden ännu mer lockande. Nu är vi i ett spännande 2018 där vi bland annat ser fram emot att passera milstolpen 1 miljon användare", säger Stefan Larsson, VD på BIMobject. Årsredovisningen finns tillgänglig för nedladdning på: http://info.bimobject.com/bimobject_data/documents/Documents/2017/bimobject-%C3%A5rsredovisning-2017.pdf För mer information, vänligen kontakta: Stefan Hansson - CFO Tel: +46 40 - 685 29 00 E-mail: press@bimobject.com ______________________________________________ Denn

Brookfield Asset Management Announces Renewal of Normal Course Issuer Bid18.5.2018 12:55Pressmeddelande

TORONTO, May 18, 2018 (GLOBE NEWSWIRE) -- Brookfield Asset Management Inc. (NYSE:BAM) (TSX:BAM.A) (EURONEXT:BAMA) ("Brookfield") today announced it has received approval from the Toronto Stock Exchange ("TSX") for the renewal of its normal course issuer bid to purchase up to 82,315,909 Class A Limited Voting Shares ("Class A Shares"), representing 10% of the public float of Brookfield's outstanding Class A Shares. Purchases under the bid will be made through the facilities of the TSX, the New York Stock Exchange ("NYSE") and any alternative Canadian trading system. The period of the normal course issuer bid will extend from May 24, 2018 to May 23, 2019, or an earlier date should Brookfield complete its purchases. Brookfield will pay the market price at the time of acquisition for any Class A Shares purchased. As at May 1, 2018, the number of Class A Shares issued and outstanding totalled 991,857,711, of which 823,159,095 shares represented the public float. In accordance with the rules

Mandalay Resources Corporation går ut med resultaten från årsstämman samt registreringen av ESTMA-rapporten och utnämningen av styrelseledamot17.5.2018 22:00Pressmeddelande

TORONTO den 17 maj 2018 (GLOBE NEWSWIRE) -- Mandalay Resources Corporation ("Mandalay" eller "Bolaget") (TSX:MND) har nöjet att meddela resultatet från årsstämman ("årsstämman") som hölls i dag i Toronto, Ontario. Alla resolutioner som presenterades vid årsstämman godkändes av aktieägarna och röstningen som skedde genom fullmakt motsvarade 79,15 % av de totalt utestående aktierna vid tidsfristen för fullmakter den 14 maj 2018. Val av styrelseledamöter Som meddelat den 14 maj 2018, har Mark Sander avgått som Bolagets President och Chief Executive Officer och drog också tillbaka sin kandidatur för återval till styrelsen. Som resultat fastställdes antalet styrelseledamöter till fem medlemmar och samtliga av de fem nominerade som fanns i bolagsledningens informationsutskick från den 13 april 2018 ("informationsutskicket"), undantaget Mark Sander, valdes om till Bolagets styrelse. Abraham Jonker förblir ledande oberoende styrelseledamot och Bradford Mills fortsätter som styrelseordförande.

I vårt pressrum kan du läsa de senaste pressmeddelandena, få tillgång till pressmaterial och hitta kontaktinformation.

Besök vårt pressrum